At 54 inches below finished grade, Evanston's design sheet says a footing is finally below frost. At 70 inches, an unprotected footing is below frost creep. Many industrial loads need to go much deeper than that. When the surface soil is soft, loose, expansive or frozen half the year, the foundation has to reach something solid.
We help owners choose and build deep foundations: driven steel piles, helical piers, micropiles, auger-cast piles and drilled shafts. The choice depends on soil, groundwater, load, access and schedule. No system is best everywhere. A pier that works on a river terrace fails on a bedrock bench, and a pile that drives easily in a basin may refuse in cobbles.
Heavy projects are coming. Uinta County commissioners approved a 1.25 gigawatt data center on 506 acres about 12 miles east of Evanston in June 2026. TerraPower's Natrium plant at Kemmerer is a 345 MW sodium-cooled fast reactor with completion expected in 2030. Large structures and heavy equipment put real demands on the ground, and the foundation decision comes first.
When shallow footings are not enough
Shallow spread footings are cheap and fast when the ground is good. They stop working when bearing soil is deep, when groundwater sits near the surface, when expansive clay swells with moisture or when loads are concentrated and settlement-sensitive. Frost adds another reason. Evanston's sheet calls for 54 inches of cover, and a deep foundation passes through the frost zone entirely.
Uplift and lateral load are the other drivers. Tall structures in high-wind sites, such as those under Evanston's 100 mph and 110 mph design winds, push on the foundation from the side and try to pull it out of the ground. Piers and piles resist both. We review the loads with the structural engineer before choosing a type, because a pier built for compression alone can fail in uplift.
Ground conditions that drive the choice
Wyoming ground varies sharply. Basin floors may have loose sands and silts. Foothills can have cobbles and shallow rock. River terraces bring groundwater. The design values the state publishes make clear how local the conditions are: Evanston requires a 40 psf minimum snow load and 60 psf in basin areas, while Teton County lists a minimum seismic design category D.
That variation is why we insist on a geotechnical report before pricing. A boring log tells us the depth to competent soil or rock, the presence of water and the risk of caving. It also tells us if we can count on a drilled shaft or need to case it. A few thousand dollars of exploration protects a large foundation budget, and we discuss the program with the owner before the rig mobilizes.
Foundation types we build
Driven piles are steel H-sections or pipe hammered or vibrated to refusal or a set load. They are fast on open sites with soft overburden. Helical piers are screwed in and tested by torque, good for lighter loads, tight access and fast starts. Micropiles are small-diameter drilled and grouted elements for low-headroom retrofits and difficult ground.
Drilled shafts, covered separately in our drilled pier foundations work, suit heavy loads, rock sockets and uplift. Pile caps, grade beams and pier caps tie the system into the structure. Where deep elements carry equipment, they connect to our equipment pads and foundations work, and we coordinate the layout so anchor bolts land correctly.
Rigs, crews and testing
Deep foundation work depends on the rig and the people running it. We schedule the right equipment for the soil and the diameter, supported by layout and survey, rebar placement and concrete finishing that we coordinate. Putting those under one plan removes the handoffs where tolerance disappears and schedule slips.
Testing is part of the work. Piles are load tested to verify capacity, helical piers are monitored for torque and shafts are inspected for depth, cleanliness and concrete integrity. A full-time inspector logs every element, and we deliver the records the engineer needs. For data center owners with tight schedules, we share daily production reports so the steel erector knows when the foundations will be ready.
Why prices differ so much
Deep foundation prices depend on depth, count, diameter, access, and ground. Hard rock or cobbles slow production sharply. Groundwater requires casing or slurry. Remote sites add mobilization, fuel and crew housing. A rig that has to travel hours and stay several weeks costs more per foot than a nearby rig for a week.
Owners can save money by finalizing loads early, testing a few elements before production and allowing the foundation contractor to propose alternates. A change from drilled shafts to driven piles, or the reverse, can move the schedule by weeks. We provide the comparison in dollars and calendar days so the decision is clear, and we show how it affects the steel on our structural steel erection schedule.
Rigs, seasons and lead times
Rigs are scarce and mobilization takes weeks. Early geotechnical work and early rig booking prevent a delay at the front end of the job. In winter, drilling can continue in frozen ground, but concrete requires heat and protection, and access over soft or icy ground can limit heavy equipment. Spring thaw closes some routes to loads.
We sequence foundation work before building starts and phase it so structural steel or tilt panels can begin as soon as the first group of piers is complete. Where a pier supports a pre-engineered building, such as a pre-engineered metal building, the anchor bolts have to be set to tolerance, and we survey each group before turnover.
Send the boring log and the load list
If you have a geotechnical report and structural loads, send them and we will compare foundation systems with costs and calendar days. If you do not have a report, we can help scope the exploration so the numbers rest on real ground.
Common Questions
How do I know if my site needs deep foundations?
A geotechnical investigation answers it. Soft or loose soils, high groundwater, expansive clay, heavy or uplift loads and settlement-sensitive equipment all push toward deep foundations. If the report shows competent soil near the surface and modest loads, shallow footings below frost are usually cheaper.
Which is faster, piles or drilled piers?
Driven piles and helical piers are usually faster per element, but they need soil that cooperates. Drilled piers take more time per element and handle obstructions, rock and large loads. The best choice depends on the site, and we compare both in the estimate.
What does frost have to do with deep foundations?
Frost lifts shallow foundations and grips the sides of shafts. Piers extend below the frost zone, and sleeves or bond breakers can reduce frost grip in the upper section. Local frost depths run from about 34 inches to 54 inches or more, so we use the figure for the jurisdiction.
Can you work in winter?
Yes, with planning. Drilling can proceed in frozen ground, and we protect concrete with heat and blankets. Access roads must carry the rig, so we stabilize or mat them. Cold increases cost but not the quality bar.
Related Pages
Related Services
Related Building Types
Related Industries
Related Service Areas
Request a project review
Tell us about the property, the building and the schedule.